Skip to main content

Canon Genset

Choosing the right diesel generator is essential for maintaining uninterrupted power supply in homes, offices, commercial establishments, and industrial facilities. A generator that is too small may struggle with heavy loads, while an unnecessarily large generator can increase purchase and operating costs.

Understanding how to calculate generator kVA requirement helps you select a generator that can handle your electrical load reliably and efficiently.

In this guide, we will explain generator sizing, load calculation for diesel generators, factors affecting generator capacity, and important considerations for generator sizing for factories and industrial applications.

What Is Generator kVA?

Generator capacity is commonly expressed in kVA (kilovolt-amperes). kVA represents the apparent power that a generator can supply.

The relationship between kW and kVA depends on the power factor.

Generator kVA Formula

kVA = kW ÷ Power Factor

For example, if the required load is 80 kW and the power factor is 0.8:

80 ÷ 0.8 = 100 kVA

Therefore, the calculated requirement is approximately 100 kVA.

However, this is only a basic calculation. Motor starting current, load characteristics, future expansion, operating conditions, and other electrical factors should also be considered before finalizing the generator capacity.

How to Calculate Generator kVA Requirement

The first step in generator sizing is understanding exactly what equipment needs backup power.

Make a list of all essential electrical loads, such as:

  • Motors
  • Pumps
  • Compressors
  • Air conditioners
  • Fans
  • Lighting
  • Production machinery
  • Refrigeration equipment
  • Computers and servers
  • Other essential electrical equipment

Step 1: Prepare a Load List

Record the rated power of every appliance or machine that may operate during a power outage.

For example:

Equipment Quantity Load per Unit Total Load
Motors 3 10 kW 30 kW
Air Conditioners 2 5 kW 10 kW
Lighting 5 kW
Pumps 1 5 kW 5 kW
Other Loads 10 kW
Total 60 kW

The total connected load in this example is 60 kW.

However, connected load and actual operating load are not always the same.

Step 2: Determine the Running Load

Not every machine necessarily operates at the same time.

For example, a factory may have 200 kW of connected equipment but only 150 kW operating simultaneously.

Therefore, generator selection should consider the maximum expected simultaneous running load, rather than simply adding every piece of equipment installed at the facility.

Identifying critical and non-critical loads can also help determine the actual backup requirement.

Step 3: Convert kW to kVA

Once the expected running load has been calculated, convert it into kVA.

For example:

Running Load = 150 kW
Power Factor = 0.8

Therefore:

Generator Requirement = 150 ÷ 0.8 = 187.5 kVA

The appropriate generator rating would then need to be evaluated based on the actual application, starting loads, operating conditions, and manufacturer’s recommendations.

Why Motor Starting Load Matters

One of the most important considerations in generator sizing is motor starting current.

Motors used in pumps, compressors, HVAC systems, production machinery, and other industrial equipment can draw considerably higher current during startup than during normal operation.

For example, a motor that consumes a certain amount of power during normal operation may require significantly higher electrical input for a short period when starting.

If a large motor starts while other equipment is already running, the generator must be capable of handling this temporary demand.

Therefore, when calculating generator capacity, consider:

  • Largest motor connected to the generator
  • Motor starting current
  • Number of motors starting simultaneously
  • Starting method
  • Direct-on-line (DOL) starting
  • Star-delta starting
  • Soft starters
  • Variable Frequency Drives (VFDs)
  • Load sequencing

For facilities with large motors or complex machinery, professional electrical assessment is recommended.

How to Choose Generator Capacity

If you are wondering how to choose generator capacity, don’t base your decision only on the total wattage of your equipment.

Consider the following factors.

1. Total Running Load

Calculate the electrical load that is expected to operate simultaneously during a power failure.

2. Starting Requirements

Check whether motors, compressors, pumps, or other equipment have high starting currents.

3. Power Factor

Power factor affects the relationship between kW and kVA and should be considered during generator selection.

4. Critical Loads

Identify equipment that must remain operational during a power outage.

For example, a factory may need to keep production machinery, safety systems, servers, lighting, and essential pumps running while switching off non-essential loads.

5. Future Expansion

If you plan to add machinery or increase production capacity, the expected future load should be considered while planning the generator system.

6. Installation Conditions

Generator performance can be affected by factors such as:

  • Ambient temperature
  • Altitude
  • Ventilation
  • Installation location
  • Cooling arrangements
  • Exhaust arrangements

These factors should be evaluated for the actual installation site.

Generator Sizing for Factory Applications

Generator sizing for a factory requires greater attention because industrial facilities can have multiple high-power machines operating simultaneously.

A factory may use:

  • CNC machines
  • Motors
  • Pumps
  • Compressors
  • Welding equipment
  • HVAC systems
  • Production machinery
  • Material-handling equipment
  • Lighting systems

Simply adding the nameplate ratings of all machines may not provide an accurate generator requirement.

A proper factory load assessment should consider:

Connected Load

The total rated capacity of all electrical equipment.

Maximum Demand

The maximum power expected to be consumed simultaneously.

Motor Starting Load

The additional demand created when motors and other equipment start.

Load Sequencing

The order in which equipment starts after generator power becomes available.

Critical Loads

Equipment that must remain operational during a power failure.

Future Load

Expected additional machinery or production capacity.

Diesel Generator Load Calculation Example

Consider a facility with the following estimated running loads:

Load Power Requirement
Production Machinery 100 kW
HVAC 30 kW
Pumps 20 kW
Lighting 10 kW
Essential Equipment 15 kW
Total Running Load 175 kW

Assuming a power factor of 0.8:

kVA = 175 ÷ 0.8

kVA = 218.75 kVA

This gives a basic calculated requirement of approximately 219 kVA.

However, the final generator selection should not be made from this number alone. Starting requirements, operating conditions, load growth, and the generator manufacturer’s specifications should also be evaluated.

Common Generator Sizing Mistakes

Choosing the wrong generator capacity can result in operational and financial problems. Avoid these common mistakes:

Selecting a Generator Only on Connected Load

Connected load does not necessarily represent actual simultaneous demand.

Ignoring Motor Starting Current

Large motors can create temporary high electrical demand during startup.

Oversizing the Generator Without Reason

An unnecessarily large generator can increase initial investment and may not operate at an appropriate load level.

Ignoring Future Expansion

A generator selected only for today’s requirement may become insufficient if significant machinery is added later.

Forgetting Site Conditions

Temperature, altitude, ventilation, and installation conditions can influence generator performance.

Not Separating Critical and Non-Critical Loads

Running every electrical load during an outage may result in a significantly larger generator requirement than necessary.

Generator Sizing Checklist

Before purchasing a diesel generator, prepare the following information:

☑ Total connected load
☑ Expected simultaneous running load
☑ Power factor
☑ Largest motor rating
☑ Motor starting method
☑ Number of motors
☑ Critical equipment
☑ Required backup loads
☑ Future expansion requirements
☑ Installation location and conditions

This information can help a generator supplier or electrical professional determine the appropriate generator capacity for your application.

Why Proper Generator Sizing Is Important

Correct generator sizing helps ensure that the generator can handle the required electrical load while maintaining reliable performance.

An appropriately selected generator can help provide:

  • Reliable backup power
  • Better load management
  • Stable operation
  • Efficient utilization
  • Reduced risk of overloading
  • Better planning for future requirements

The objective should not simply be to select the largest generator available. The generator should be appropriately matched to the application’s electrical requirements.

Choose the Right Generator with Canon Genset

Selecting the right diesel generator requires more than a simple kW-to-kVA conversion. Running loads, motor starting requirements, power factor, critical equipment, future expansion, and site conditions should all be considered.

Canon Genset provides diesel generator solutions for residential, commercial, and industrial applications. With generator capacities available for different power requirements, the right solution can be selected according to your application’s specific needs.

If you are planning a generator installation for an office, commercial facility, manufacturing unit, or factory, share your load details and application requirements with the Canon Genset team for appropriate guidance.

Canon Genset – Trusted Power Solutions Since 1967.

Frequently Asked Questions

How do I calculate generator kVA requirement?

Calculate the expected running load in kW and divide it by the power factor.

Formula: kVA = kW ÷ Power Factor

Motor starting requirements and site conditions should also be considered before final selection.

How do I calculate load for a diesel generator?

Prepare a list of all equipment requiring backup power, calculate the expected simultaneous running load, consider power factor and starting loads, and then determine the appropriate generator capacity.

How do I choose generator capacity for a factory?

Factory generator sizing should consider connected load, maximum demand, motor starting current, production machinery, critical loads, load sequencing, site conditions, and future expansion.

Can I select a generator based only on kW?

kW alone is not sufficient for final generator selection because generator ratings are generally expressed in kVA and the power factor and starting characteristics of the loads also matter.

What happens if a generator is undersized?

An undersized generator may become overloaded when the connected load exceeds its rated capacity. High starting loads can also cause voltage or frequency disturbances.

Is a larger generator always better?

Not necessarily. Generator capacity should be appropriately matched to the actual application and operating requirements rather than selected solely on the basis of maximum available capacity.

Call Now Button